1.Check clearance between piston rings and ring grooves. If the limit is exceeded, replace
piston rings or piston, or both. Standard value:
No. 1 ring: 0.02 - 0.06 mm No. 2 ring: 0.02 - 0.06 mm
Limit: 0.1 mm
|

|
2.Put piston rings into the cylinder bore, press them against the piston top face, and push
them in. After achieving squareness, measure the end gap with a free gauge. If the end gap is
excessive, replace piston rings. Standard value:
No. 1 ring: 0.18 - 0.28 mm No. 2 ring: 0.28 - 0.43 mm Oil ring: 0.10 - 0.40 mm
Limit:
No. 1 ring: 0.8 mm No. 2 ring: 0.8 mm Oil ring: 1.0 mm
|
|
|
1.Wipe oil off the crankshaft pin and connecting rod bearing.
|
|
|
2.Place a plastigage in length equal to the bearing width on the pin shaft straight
in alignment with the shaft centre.
|

|
3.Carefully install the connecting rod cap and tighten bolts to the specified torque of
5.0 N·m → 20 N·m → +90°. 4.Remove bolts and gently remove the connecting rod cap.
|

|
5.Measure the crushed plastigage width (area most widely crushed) using a scale printed
on the plastigage bag. Standard value: 0.026 - 0.053 mm Limit: 0.1 mm
|